CITIC Pacific Mining will directly manage the construction and commissioning of production lines 3-6. Given the experience the MCC team has accumulated through the construction of the first two production lines, key members of the MCC team have been seconded to CPM to assist with the works. The remaining works will primarily involve construction and commissioning of 3rd and 4th crushers, four production lines at the concentrator, 3rd and 4th filter buildings at the dewatering plant and 2nd stacker at the stockyard. During the peak construction, approximately 1400 people will work on the project.